Reckitt Benckiser – Mechanicsburg, PA

  • Total site preparation for 812,240 SF distribution center
  • 200,000 CY of excavation
  • 130,000 CY of rock removal
  • 19,600 SY of asphalt paving
  • 12,500 LF of storm sewer and sanitary sewer piping
  • 6,400 LF of water main piping