City of Taneytown WWTP
City of Taneytown WWTP
▪ The City of Taneytown WWTP project consisted of the construction of a new BioMag system that was incorporated into the existing Enhanced Nutrient Removal System (ENA), including the installation of BioMag equipment, blowers, pumps, magnetite recovery equipment, course bubble diffusers, carbon feed system, and all inter-connected piping. The WWTP also required a new concrete sludge holding tank, upgrades to the SBR system, and replacement to the existing ACAPA systems.
▪ General Construction
▪ Design Flow: 1.1 MGD, Peak Flow 3.5 MGD